Site Update Report — Current Progress Across Projects 134, 135 & 136
Overview
Our team at Allen Brothers Construction is progressing through three major projects across Brisbane — each at a different stage of construction and each showcasing the engineering, craftsmanship and architectural detail that define our work. Below is the latest update across Project 134 (Corinda), Project 135 (Grange) and Project 136 (Bulimba),summarising recent milestones and upcoming works.
Project 134 — Major Architectural Renovation, Corinda
Project 134 has now close to lock‑up stage, marking a major milestone in the structural and external completion of the home. The internal plastering works have recently been completed, and the roof — including all suspended slab sections — is fully installed.
Recent Progress
Lock‑up stage achieved (except garage door)
Internal plasterboard installation and finishing completed
Roof and suspended slab sections fully installed
Structural framing and multi‑level integration complete.
Upcoming Works
Tiling throughout wet areas and architectural zones
Pool fencing installation
Cabinetry installation (kitchen, bathrooms, laundry, custom joinery)
Interior detailing and finishing
This project continues to demonstrate the precision required for raise‑and‑build‑under transformations in Brisbane’s riverside suburbs.
Project 135 — Custom New Build, Grange
Project 135 has reached a major external milestone, with roof installation underway and external cladding progressing across the façade. The carpentry team has completed the ProClima WRB wrap, and Linea weatherboard cladding is now being installed. A key achievement was the successful crane installation of the precast Plungie pool — a central feature of the outdoor living area.
Recent Progress
ProClima WRB installation to all external walls
Linea weatherboard cladding commenced
Roof framing completed; roof sheeting underway
Precast Plungie pool craned into position
Early landscaping preparation around pool zone
Upcoming Works
Completion of weatherboard cladding
External painting and scaffold removal
Air‑conditioning, electrical and plumbing rough‑ins
Plasterboard installation and setting
Preparation for internal fit‑out and detailing
This project reflects the demand for premium custom homes in Grange, Wilston, Alderley and Newmarket — suburbs known for elevated blocks, character streetscapes and design‑led renovations.
Project 136 — Raise & Build‑Under, Bulimba
Project 136 is progressing through its structural transformation, with the house raise completed and the lower‑level formation underway. Temporary supports are in place, excavation has been completed, and engineering inspections for the house position have passed.
Recent Progress
Full house raise completed
Temporary structural supports installed
Excavation and lower‑level preparation
Engineering inspections passed
Upcoming Works
New slab pour
Blockwork and structural framing
Integration of upper and lower levels
Roofing and external envelope works
Bulimba continues to be a high‑demand suburb for raise‑and‑build‑under projects due to its character homes, riverside positioning and premium lifestyle appeal.
Across Brisbane’s inner‑south and inner‑north suburbs — particularly Corinda, Grange and Bulimba — demand continues to grow for luxury architectural homes that emphasise design quality, spatial performance and long‑term liveability. These neighbourhoods are known for their established streetscapes, larger allotments and a blend of character and contemporary housing, creating strong opportunities for high‑end architectural renovations, multi‑level redesigns and raise‑and‑build‑under transformations.
Homeowners in these areas increasingly prioritise thoughtful architectural planning, premium material selections and refined interior detailing. This shift toward design‑driven construction is shaping the next generation of luxury homes across Brisbane’s riverside and inner‑city suburbs, with projects focusing on longevity, craftsmanship and elevated lifestyle outcomes.